Type Concrete slab construction, Airport construction
Runtime08.2014 - 09.2015

Upgrade for Oradea Airport

The extension and modernisation works at Oradea Airport saw the existing runway of the airport extended by 300m to a length of 2,100m and a width of 45m. To ensure that the interruption to air traffic would be kept to a minimum, the main works on the runway were completed in just 59 days.

In addition to the expansion of the runway, the PORR project also involved building two new taxiways with lengths of 144.5 and 750m, as well as a new apron on which six aircraft can be processed simultaneously. The modernisation measures included replacing the drainage system and the power supply, along with new airfield lighting.