Chrudim hot-water pipeline and hot-water transfer station
Daten und Fakten
Firma | PORR a.s. |
Auftraggeber | Elektrárny Opatovice, a.s. |
Stadt/Land | Chrudim - Tschechische Republik |
Projektart | Pipeline construction |
Bauzeit | 06.2013 - 09.2014 |
Heating Chrudim.
This project involved laying a total of 3,736m of district heating hot-water pipes and installing eleven transfer stations.
PORR was responsible for all earthworks for this project, including excavating and subsequently backfilling trenches, creating pipeline beds and demolishing and replacing asphalt surfaces, pavements and other paved areas. A 200mm thick steel-fibre concrete road surface layer was also included in the project.