N02, EP Acheregg tunnel and Lopper viaduct

Facts and Figures
Company PORR SUISSE AG
Principal Federal Roads Office [ASTRA]
Location Hergiswil - Switzerland
Type Rock technology
Runtime 09.2009 - 12.2010

Safe travel ahead.

Before the PORR team was able to commence work on the safety measures required by this project, the rock face, which was heavily overgrown in places, first had to be cleared and cleaned. Then the required works could begin: the drilling and anchoring of the rock nails and anchors necessary for securing the safety nets. These works were carried out from scaffolding with only one lift for access.

More than 3,000m2 of steel mesh netting now protects the Lopperstrasse, between the Acheregg tunnel and the Lopper viaduct, from rockfall and avalanche.